SNC-Lavalin was awarded the engineering, procurement and construction contract for the 60,000-tonne district cooling plant in mid-June 2023, on a 27-month term (Saudi Gulf Projects).

What it works on

EPC contractor (27-month contract, June 2023)

District Cooling Plant

Saudi Gulf ProjectsJun 2023

Timeline

13 Jun 2023Construction

District cooling plant contract awarded to SNC-Lavalin

SNC-Lavalin received a 27-month EPC contract for the park's first district cooling plant, with an ultimate capacity of 60,000 refrigeration tonnes.