Infrastructure package

Phase 2 infrastructure

Six bridges and the networks for the eastern phase

Under constructionas of Nov 2025 Phase 2

Works under way since Nov 2025 per MEED.

Freyssinet lists a Phase 2 infrastructure contract of SAR 3.2 billion over 30 months, with six bridges. MEED reported that Haif began $480 million (about SAR 1.8 billion) of Phase 2 works in November 2025. The two figures appear to describe the same joint venture at different scopes, which is our hypothesis, not a confirmed split.

Key facts

Total contract (Freyssinet) SAR 3.2 billion Freyssinet Saudi Arabia Total Phase 2 infrastructure contract per Freyssinet · as of Jan 2026
About SAR 1.8 billion ($480m) MEED MEED, Nov 2025; probably the Haif share of the joint venture, not the total · Nov 2025
Medium confidence

Sources

  1. Industrial Facilities - Freyssinet Saudi Arabia · Freyssinet Saudi Arabia
  2. Contractor begins $480m King Salman Park infrastructure works · MEED, 5 Nov 2025
  3. Our projects - Haif Company · Haif Company

The monthly King Salman Park briefing

What opened, what was awarded, what changed. One email a month, sourced.

Suggest a correction

We welcome corrections from the project team, journalists and readers. Please include a source link if you can.