Haif, a Riyadh contractor founded in 1976, shared the Phase 1 infrastructure joint venture with Freyssinet. MEED reported on 5 November 2025 that Haif had begun Phase 2 infrastructure works worth about $480m (SR1.8bn), awarded in July 2025. Freyssinet lists the Phase 2 total at SR3.2bn, and the two figures probably measure a share and a whole; the split between the partners has not been published.
What it works on
Operations and Maintenance Building
Freyssinet Saudi ArabiaPhase 2 infrastructure
SAR 1.8bn contract value
MEEDNov 2025Haif CompanyTimeline
Site-wide infrastructure package begins
The Freyssinet and Haif joint venture reports starting the site-wide package in September 2021, covering about 13 square kilometres of roads, drainage, irrigation, power and data.
Plan for the first infrastructure package: finish by March 2023
The contractor's profile gives 18 months from September 2021, so March 2023, for the site-wide infrastructure package. Phase 2 infrastructure followed in 2025.
Haif awarded Phase 2 infrastructure
MEED reported the award in July 2025 at about SAR 1.8bn (USD 480m). Freyssinet lists a larger SAR 3.2bn Phase 2 contract for the joint venture, so the two figures measure different things.
Phase 2 infrastructure works begin
Haif started roads, power, water, irrigation, sewage, stormwater and district cooling works for the second phase.